The pipes leave the factory already fitted with a protective external PE coating, though the ends remain uncoated to allow for joining and welding.
A primer layer is applied first; this acts as an initial barrier against corrosion and creates an ideal surface for the adhesion of subsequent treatments.
If necessary, the surfaces are first brought to the optimal temperature for applying the primer and other protective materials.
An epoxy coating is applied around the joint; once cured, it forms a flexible, dielectric coating that seals the connection between the two sections, thereby preventing potential air or water infiltration.
Upon completion of the treatment, the joints are inspected for any air bubbles, porosity, or cracks.
The photo shows our operators applying the coating sleeve to industrial pipe joints inside a concrete containment structure.